Construction Has Begun In Kyiv On Pontoon Bridges Connecting The Two Banks
- 18.11.2026, 15:58
The deadlines for completing this work have been announced.
Construction has already begun in Kyiv on pontoon crossings over the Dnieper River, which are intended to ensure minimal traffic flow and allow key vehicles to pass in the event of critical damage to or destruction of bridges. This work could be completed within two to three months.
This was announced by the head of the Desnianskyi District State Administration in Kyiv, Maksym Bakhmatov, in a podcast RBC-Ukraine.
Plan “B” for Logistics
Responding to a question about whether there is a contingency plan for transportation between the two banks of Kyiv in case the bridges cease to function, Bakhmatov noted that there are no large-scale solutions like tunnels yet, but the city has already moved on to the practical construction of pontoon crossings.
“When it comes to conceptual ideas—tunnels and so on—no one knows what to do. The only thing being done right now is the actual construction of crossings. We’ve started building them. They’ll be finished within 2–3 months. There’s a chance they’ll be finished,” said the head of the Desnianska District State Administration.
According to him, these are specifically pontoon crossings designed for minimal traffic and the passage of emergency vehicles and essential vehicles.
Attack on Kyiv’s Bridges and Current Traffic Plan
On the night of November 17, Russian troops launched a ballistic missile strike on Kyiv’s bridges. Following the attack, the North and South Bridges were completely closed, and temporary restrictions were imposed on other crossings.
As of November 18, traffic on the South and North Bridges had been partially restored, but significant restrictions and temporary traffic patterns remain in effect in the city:
Southern Bridge: Vehicles weighing up to 10 metric tons and public transportation vehicles weighing up to 18 metric tons are permitted to cross at regulated intervals; however, travel from the right bank to the left bank remains closed.
Northern Bridge: Open only to public and special-purpose vehicles in the far-right lane in both directions. Passenger cars and transit freight vehicles are prohibited.
Paton Bridge: Operating under alternating traffic patterns (from 6:00 a.m. to 4:00 p.m. — from the left bank to the right; from 4:00 p.m. to midnight — in the opposite direction).
Podil Bridge: Traffic from the left bank to the right bank is temporarily restricted for approximately 15 minutes following the announcement of an air raid alert.
Darnitsky Bridge and Metro: operating without restrictions.
In addition, starting today, November 18, at 1:00 p.m., for safety and technical reasons, the automatic traffic violation detection systems on the North and South Bridges have been temporarily deactivated in both directions.